Silesian - dhismuhu wuu sii socdaa

Silesian - dhismuhu wuu sii socdaa.

Ma aanan ka warbixin shaqada markabka ilaaliyaha ee Ślązak muddo dheer, wax badan ayaa dhacay bilihii la soo dhaafay. Waxaa loo diyaarinayaa tijaabo badda ka dibna badda markii ugu horeysay. Horumarka uu marayo markab xanuun ku jiro ayaa laga arki karaa dibadda iyo gudaha,sida aan ku soo bandhigi doono warbixintan.

Laga soo bilaabo markii markabka la bilaabay July 2, 2015, shaqadu waxay ahayd inay ka bilaabato "laga bilaabo dhulka." Nasiib darro, dhibaatooyin hor leh ayaa soo kordhay, taas oo keentay in dib u dhac kale uu ku yimaado barnaamijka, markan oo la xidhiidha heshiisyada ku jira Lifaaqa No. 15 ee Heshiiska No. 1/BO/2001 ee ku taariikhaysan 27, oo uu saxeexay mas'uulkii masruufka. hantida Stocznia Marynarki Wojennej SA ee dacwadaha kicitaan ee Gdynia oo ay la socdaan Kormeeraha Hubka ee Wasaaradda Difaaca Qaranka (IU), 2001 Sebtembar 23 ee Gdynia, taas oo badashay ujeedada corvette asal ahaan loo dhisay markabka ilaalada Ślązak. Sababta ugu weyn ee dib u dhigista keentay waxay ahayd dhibaato xagga diyaarinta dhismo gaar ah oo loogu talagalay rakibaadda nidaamka dagaalka isku dhafan (ICS), nadaamka navigation isku dhafan (INS) iyo habka isgaarsiinta isku dhafan (ICS). Nidaamyadan waxaa lagu keenay iyadoo lagu salaynayo qandaraasyo ay kala saxiixdeen Diisambar 2013, 12 Wasaaradda Dhaqaalaha iyo IU ee Thales Nederland BV iyo Thales Electronic Systems GmbH. Daahitaanka ayaa saameyn ku yeelan doona kharashyada la xiriira adeegga iyo dammaanadda kordhinta qalabka iyo qalabka ay bixiyaan alaab-qeybiyeyaal iyo qandaraasle-hoosaadyo.

Hadda, IU waxay heshiis la gashay qandaraaslayaasha, ie. SMW, Thales Nederland iyo Enamor Sp. z o. o., Jadwal cusub oo shaqada markabka, marka loo eego imtixaanada xambaarka (HAT, Tijaabada Ogolaanshaha Harbor) waxay bilaabanayaan Abriil, iyo tijaabooyinka badda (SAT, Tijaabada Ogolaanshaha Badda) - qeybtii labaad ee sanadkan. waxayna socon doontaa ilaa dhamaadka May 2018. Wareejinta la filayo in lagu wareejiyo Ciidanka Badda Polish waa in ay dhacdo Julaay 2018. Inkasta oo ay adag tahay in la rumaysto, wakhtiga kama dambaysta ah ayaa sidoo kale laga yaabaa in la dhaafo ... "Shipyard"), taas oo ay u badan tahay in ay raaci doonaan kormeer iyo isbeddel ku yimaada goobta markabka, taas oo hubaal ah in aan gacan ka geysan doonin habsami u socodka dhismaha. Si kastaba ha ahaatee, IU waxay hubisaa inay qaadayso tillaabooyin lagu dhimayo khatartan. Nasiib darro, silbasho gaar ah ayaa durba la dareemay - GAT weli ma bilaaban (sida muuqata sababo rasmi ah oo ah in barnaamijka Imtixaanka aysan ansixin waaxyaha milatariga), waxayna dhici kartaa bilaha xagaaga. Xaaladdan oo kale, duulimaadka ugu horreeya waxa la filan karaa oo kaliya xilliga dayrta.

Dibedda

Isbeddelladan ayaa iska cad inay yihiin kuwa ugu muuqda. Isku dhafka anteenooyinka hubka iyo qalabka elektaroonigga ah ayaa markabka ka dhigay mid dhameystiran.

Juun 15, 2016, horumar astaan ​​ah ayaa dhacay. Markabku wuxuu helay hubkii ugu horreeyay oo isla markiiba ugu cajiibsanaa - 76-mm L / 62 Super Rapid automatic cannon universal. Soo saaraheedu waa OTO Melara Sp.A. waxay ka tirsan tahay kooxda warshadaha ee Leonardo. Qoyska qoryaha 76-mm ee shirkaddan ayaa si fiican loo yaqaan ma aha oo kaliya adduunka, laakiin sidoo kale dalkeena. Labada markab waxay leeyihiin hal Mk 75 turret, kaas oo ah koobiga noocii hore ee Compact.